Many companies recognise that simulation modelling can significantly reduce the risk associated with major change. A recent project at Carlsberg-Tetley’s Northampton Brewery resulted in an envisaged requirement to install a third filter at a cost of £1m being avoided whilst the requirement to increase capacity by 33% was met. The best solution, identified through modelling, was not the obvious one.
'사례연구 > 식음료.제약' 카테고리의 다른 글
| Lanner Helps AstraZeneca Gear up for a World Bestseller (0) | 2010/05/20 |
|---|---|
| WITNESS Helps Bayer Sell Automated Laboratories (0) | 2010/05/19 |
| Expanding Capacity at Carlsberg-Tetley (0) | 2010/05/19 |
| DIAGEO : Good things come to those who … Improve! (0) | 2010/05/19 |
| Glaxo Increases Packaging Line Productivity by 15% (0) | 2010/05/19 |
| Golden Wonder improve manufacturing performance (0) | 2010/05/19 |
TAG
simulation
Carlsberg-Tetley.pdf